KARGIL, SEPTEMBER 25, 2021
In order to review the progress of utility shifting on Kargil Zanskar National Highway NH-301, Additional Deputy Commissioner Kargil Tsering Motup convened a meeting of the concerned officers here today.
Assistant Commissioner Revenue (ACR) Abdul Gaffar Zargar, General Manager National Highways and Infrastructure Development Corporation (NHIDCL) Ashwani Kumar, Captain Bharat Garisson Engineer Executive Khumbathang, Administration Commandant Khumbathang, Executive Engineer SVD Sankoo, officers from PDD, Horticulture and Forest besides other concerned officers were present during the meeting.
READ MORE :-Directors of IIT Delhi, Mumbai, Kanpur visit Kargil
During the course of the meeting, detailed discussions and deliberations were held on various measures of utility shifting on National Highway NH-301.
ADC Kargil directed the concerned officers of PDD and NHIDCL to work in close coordination with the Army Unit at Khumbathang to relocate electric poles at the edge of the 12-meter approved span for road widening.
With regard to the estimated cost of structures which are going under road construction, ADC Tsering Motup directed the concerned officers of PWD to prepare the estimated cost of the structures in consultation with the Revenue Department.
Meanwhile, the ADC directed the concerned officers of Horticulture and Forest Department to mark the fruit-bearing and non-fruit bearing trees at the earliest possible, and make proper estimates for payment of compensation to the concerned families.