POONCH, JUNE 02, 2021: District Development commissioner poonch ,Inder Jeet today chaired a meeting of concerned officers to review the progress of development activities taken up under B2V3 Programme in the District by different departments.
The meeting was informed that under B2V 3 most of the works have been completed, while the rest are at different stages of completion. Besides, it was informed that majority of works have been tendered, while the tendering of the rest is underway.
The ACD, Poonch informed that tenders for 475 RDD works were floated and of which 120 works have been allotted to the execution agencies and allotment for rest would be done within 1-2 days.
The XEN R&B informed that out of 13 works under B2V3, 5 have been completed and the rest are at different stages of completion.
Similarly, XEN PHE Stated that out of 25 work, 6 have been completed, 3 are near completion and tendering for rest is in process.
The DDC directed the Power Development Department to complete 235 works identified under B2V3 within 45 days.
The DDC directed XEN , Jal Shakti Department to float open tenders for executing the works for Ground water Division.
The DDC directed the concerned officers to complete the tendering process and ensure the completion of all the identified
Assistant Commissioner Development, SSP, Tehsildar Mandi, XEN PWD, XEN PHE, DPO, CEO and all BDOs attended the meeting.